WORKS HAVE COMMENCED
Mounties Group have pledged to provide first-class amenities for spectators, including comfortable seating, sports-grade lighting, and a newly constructed bowler's lounge. Situated with a commanding view of the green, this refined space will enable our esteemed members and guests to view the excitement year-round. Be sure to keep an eye on our social media pages as we bring you regular updates. This is an incredibly exciting time for Halekulani Bowling Club and the local community! .Â
Be sure to keep an eye on our social media pages as we bring you regular updates.
This is an incredibly exciting time for Halekulani Bowling Club and the local community!
Where are we up to?
CC2 application has been lodged on the planning portal with Construction Certificate issued Friday 1/11
Steel barrels are painted (see below pic) & will be transported to site next week with crane in position week commence 15/11 to commence erecting the structure
Â
Â
CURRENT
Synthetic Surfaces will commence surface works end of November, break for Xmas and return mid-January to complete works
The build program is currently on time and is subject to delays by any wet weather / high winds during construction of the structure
Carpet is in storage at Perth and will be transported to site in January
Hydraulic works commenced (stormwater & drainage)
New footpath works adjoining Club/bowling green have commenced
Blown lights for Green 2 will be replaced by builder when high access equipment is onsite
Fitout continues to track well in the new bar / greenkeepers shed
Â
Â
Undercover Green - Lights Installed
19 November 2024
Update
6 November 2024
Structure Installation Complete
12 November 2024
Update
6 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Update
5 November 2024
Steel Work for undercover structure.Â
18 October 2024
Greenskeeper shed deomolished
25 September 2024
Demolition began 22 February 2024
Demolition completed mid March 2024